Short answer: multiply length × width × thickness in feet, divide by 27. Enter your dimensions below and you'll have the exact answer — yards, bags and cost — as you type.

ft
ft
in
$USD

Concrete needed

2.96 yd³

80.0 ft³

Estimated cost

$489

at $165 per yd³

Approx. weight

10,640 lb

≈ 5.3 tons

Bagged mix

134

80-lb bags

178

60-lb bags

267

40-lb bags

Before you order: add about 10% for uneven subgrade and spillage — that's 3.26 yd³ or 147 × 80-lb bags.

Formula

The whole question comes down to one line of math:

cubic feet = length (ft) × width (ft) × [thickness (in) ÷ 12]
cubic yards = cubic feet ÷ 27

Why 27? A cubic yard is a 3 × 3 × 3 ft cube. Bag counts are the same volume in sack form: an 80-lb bag yields 0.60 ft³, a 60-lb bag 0.45 ft³, a 40-lb bag 0.30 ft³ — round up to whole bags.

Example

  1. Backyard patio 14 ft × 10 ft, 4 inches thick: 4 ÷ 12 = 0.333 ft.
  2. Volume: 14 × 10 × 0.333 = 46.7 ft³.
  3. Yards: 46.7 ÷ 27 = 1.73 yd³ — order 2 yd³ with the 10% allowance.
  4. Bags instead: 46.7 ÷ 0.60 = 77.8 → 78 × 80-lb bags (86 with waste).

Frequently Asked Questions

How do I calculate how much concrete I need?

Multiply length × width × thickness, all in feet, to get cubic feet — then divide by 27 for cubic yards. If thickness is in inches, divide it by 12 first. The calculator above runs that math as you type, then adds the 10% ordering allowance for you.

How much concrete do I need for a 12×20 slab?

At 4 inches thick: 2.96 cubic yards (80 ft³) — order about 3.3 yards, or in bags, 147 × 80-lb with the allowance. At 6 inches the same footprint needs 4.44 yards, so thickness matters more than anything.

Should I measure in feet or inches?

Measure length and width in feet and thickness in inches — that's how slab work is actually specified (a '4-inch slab'). The calculator handles the conversion; just don't mix units on paper.

How accurate is the estimate?

The math is exact for a rectangular pour; reality adds variance. Uneven excavation, form flex and spillage are why the standard practice is ordering 10% extra — the 'before you order' line in the result already includes it.